Areas of Expertise

Dams and Energy Projects

DAM PROJECTS
6 Dam Constructions for irrigation and security purposes have been completed.

HEPP PROJECTS 
5 HEPP Projects including dam and weir types have been completed.

NATURAL GAS COMBINED CYCLE POWER PLANTS
One NGCCPP Project which is also an AGE Investment has been completed.


Within the scope of dam and energy works, until 2017:

  • 12 Projects of USD 772,000,000 have been completed.
  • 3 Projects worth USD 608,000,000 are still in progress.
  • Total Installed Capacity of Completed HEPP Projects: 271 MW
  • Total Installed Capacity of HEPP Projects in Progress: 525 MW
  • Total Installed Capacity of the completed CCPP Project: 205 MW
  • Total Installed Capacity of Committed Energy Projects: 1,001 MW

Infrastructure Projects

Below listed projects are within the Infrasturcture section;

  • Potable Water Projects: Network and Transmission Lines, Reservoirs and Pump Stations are constructed
  • Sewage Projects: Network and Transmission Lines, Pump Stations and Deep Sea Discharge works are built.
  • Landscaping Projects: Landscaping and Stripping works are built.
  • Oil Transportation: Crude Oil Transmission Pipelines are constructed.

Infrastructure activities until 2017:

  • 10 Projects are completed with a total cost of 121,800,000 USD.
  • 1 Project is ongoing with a total cost of 13,600,000 USD.
  • Pipes of 525,957 m in various diameters and types are laid.
  • 8 Reservoirs with a total capacity of 100,000 m³ have been constructed.

Superstructure Projects

Within the scope of superstructure works until 2017, 59 projects of USD 553,100,000 have been completed. And the total construction area with these projects is 1,366,514 m².

Irrigation Projects

Within the scope og irrigation projects, 17 projects worth 537,300,000 USD has been completed by AGE Construction. Total irrigated area with these projects is 115,790 Ha.

The total cost of 7 projects in progress is 254,200,000 USD and the total irrigated area is 76,466 Ha.

Transportation Projects

47.5 kilometers of highway with 2 projects and 3,235 meters of metro lines with 1 project had been completed by AGE Construction. 

Suleymania Airport which has 1,000,000 annual passenger capacity has also been completed within the scope of our transportation projects.  

The total value of our 8 completed projects in transportation area is 101,100,000 USD.

38,000 m of Railway Tunnel is being constructed with 2 ongoing projects on Himalayan Belt. The total cost of our ongoing transportation projects is 360,000,000 USD